The pipes under Shores Estates are in the ground and tested. The pump station passed its test in September, and final milling and paving for the last project streets was scheduled for October 19 through 23, 2026. Every house in the neighborhood still runs on a septic tank. The Village has said the system is not open for residential connections, and owners should not start connecting or abandoning their tanks until they get formal notice.
That gap is important for anyone with a Shores Estates home under contract this fall. Some details of the sewer project are already set, while others are still undecided. The connection period has no announced start date, the subsidy's structure has changed several times, and the public notice does not state the total term of the annual charge.
What is already settled, and what is not
Miami Shores Village has posted monthly project updates on its Shores Estates Septic to Sewer Conversion page. Read together, they divide into two groups.
| Item | Status as of late October 2026 |
|---|---|
| Sewer main, laterals, pump station | Built and tested |
| Location of each home's lateral | Fixed. Laterals cannot be moved once installed |
| Annual wastewater assessment | $1,163 per parcel for the fiscal year that began October 1, 2025 |
| Assessment term in years | Not stated in the published notice |
| Residential connections | Not open; start date not announced |
| Home connection assistance program | In draft, awaiting Village Manager and Council approval |
| Who permits the work | Miami Shores for building and plumbing, Miami-Dade DOH for septic abandonment |
| Restoration at the east end of NE 105th St | Wall rebuild waits for a separate drainage project, with a temporary barrier proposed for now |
The settled items are mostly physical, and the open ones are mostly financial and procedural. The rest of this post follows the open column, because that's where a buyer and seller will end up negotiating.
The physical facts were locked during construction
Some details buyers tend to assume they can change are already fixed. During construction, residents could choose where their sewer lateral would meet the property. Where no preference was submitted, the contractor picked the spot based on site conditions. The Village's FAQ says plainly that once installed, "these lateral connections cannot be moved."
That matters because the Village says connection and abandonment costs depend on individual property conditions, "such as distance to the sewer main and plumbing modifications needed for connection." A lateral on the far side of the lot from the home's existing plumbing means a longer run on private property. The Village's final location map is posted on the project page. A buyer can compare it with where the house's plumbing exits today.
The FAQ also notes that some homes in Shores Estates may have two septic systems. Septic abandonment is permitted and inspected by the Florida Department of Health in Miami-Dade, not by the Village, and the Village doesn't prescribe an abandonment method. The department's onsite sewage page confirms that county health offices handle septic permitting and inspection.
The connection period has no announced start date yet
The Village says it will notify everyone when the connection period officially begins. In an August 2026 interview with the Biscayne Times, Public Works Director Delroy Peters said the project should be finished by December 2026: "And then, once we close it out, then by next year we start talking about the connection."
As of late October 2026, the Village has not announced a start date for the connection period. A home that changes hands this fall changes hands before that date is known, and how a contract deals with it is a question for the parties and their attorneys.
The subsidy has changed shape three times
Funding to help with connection costs exists. How it gets used has changed throughout the project, and that change is the main reason a buyer today can't estimate what connecting will cost.
- November 2025. The Village said it had secured public funding to offset connection costs. Because the money was public, it planned to hire a single contractor for all connection work under one contract. The program would be opt-out, so every eligible home was included unless the owner formally declined.
- July 2026. The plan was still for the Village to manage connections for participating residents. It also acknowledged that some owners might prefer their own contractor and promised a survey on funding options. Because the money came from the State, any distribution method needed coordination with the Florida Department of Environmental Protection and approval from the Village Council.
- September 2026. The Village was weighing a hybrid. Residents could join a Village-managed program or hire their own licensed professionals. The Village said it had funds to help offset both connection and septic abandonment costs and was still deciding with FDEP how to deploy them. It added that building and plumbing permits would go through Miami Shores, not North Miami.
- October 2026. The program details were "still in draft form." The Village said it would seek Manager and Council approval before sharing them, with more details planned by the end of October.
The Village of North Miami will operate the system. The Biscayne Times reported that Village Manager Esmond Scott said staff used $1 million left over from the project to cover the utility's connection charge. The private side of the job is a separate question: the plumbing run from house to lateral and the tank abandonment. That private work is what the draft program is meant to address.
The Village's FY2027 adopted budget includes a $725,000 line labeled "Southeast Septic to Sewer DEP Funding." The budget page doesn't say that figure is the Shores Estates homeowner subsidy, and it shouldn't be read as one.
The assessment arrives before the sewer does
The connection program is still open, but the annual charge started first. The Village published a notice of hearing to impose a non-ad valorem wastewater assessment on Shores Estates parcels under Resolution 2025-23, adopted July 1, 2025. Each residential parcel is assigned one Equivalent Benefitted Unit. The rate for the fiscal year beginning October 1, 2025 was $1,163 per unit, with about $122,535.50 in total collections, including the cost of collection.
The assessment is collected on the regular property tax bill, starting with the bill mailed in November 2025. The notice warns that nonpayment leads to a tax certificate against the property. In August 2026, the Biscayne Times noted that residents were already paying the $1,163 annual charge even though the system hadn't been switched on.
The published notice gives the per-unit rate for one fiscal year without saying how many years the assessment will run. The Village's FAQ describes the system's cost as paid "over time through a unified method of assessment." The resolution and the preliminary assessment roll can be inspected at the Village Clerk's office.
A second project is already changing the first one's finish
The October update added something no earlier update mentioned. The Village received new funding information about a stormwater improvement project planned for Shores Estates, a project that had "been stuck for several years at the State and Federal level." Staff called it imminent but gave no date.
That news changed the sewer project's finish. On NE 105th Street, the contractor will repair the sewer trench, potholes and other damage from the project. The broader roadway and swale restoration that was planned earlier is dropped, and the swale work is being folded into the drainage project. The temporary 20-foot opening in the wall at the east end of NE 105th Street, cut for construction access to the pump station site on the Biscayne side, won't be rebuilt until the drainage work is done. The Village plans to propose a temporary barrier in the meantime.
For a buyer touring this fall, the street, swale and wall they see are an interim condition, not what the finished neighborhood will look like. The pump station sits on the former Miami Shores Motel site at 10500 Biscayne Boulevard, according to the Biscayne Times. The Village says it is holding off on the wider restoration and the wall rebuild so the drainage project doesn't disturb new work soon after it is finished.
Questions buyers and sellers raise
Can a buyer connect the house right after closing? No. The system isn't open for residential connections yet. The Village has asked residents not to begin connection or septic abandonment until it gives formal notice.
Who handles permits for the work? Building and plumbing permits for home connections go through Miami Shores Village. Septic abandonment goes through the Florida Department of Health in Miami-Dade septic tank office at 11805 SW 26 St., 786-654-6620.
Where do project questions go? Miami Shores Village Public Works is at 305-795-2210. Director Delroy Peters and Assistant Director Jorge Loor are listed as contacts on the project page.
Where will the connection program details appear? The Village planned to share them by the end of October, after Manager and Council approval. Once approved, the details will appear on the Village's project page. Until then, the cost of the private connection work stays an estimate.
This post is general information about public records and state law, not legal, tax or financial advice. Confirm how the assessment, the connection deadline and any assistance program apply to a specific property with the appropriate attorney, tax professional or the Village directly.
If you own a home in Shores Estates and plan to sell, the assessment, the fixed lateral location and the open program terms all affect how a buyer will value your house. Eric Davis Inc. can prepare a valuation that accounts for each of them and help you decide how to present them to buyers from the start. Get a Free Home Valuation.